We have requirement to set start date and end date only for a set of entitlements in an endpoint. But the feature is enabled for all the entitlements in that endpoint. Please let us know incase of any similar implementation done to restrict this feature only for certain set of entitlements only. 

Saviynt ticket raised for the same - 1630822

7 REPLIES 7

rushikeshvartak
All-Star
All-Star

Use endpoint level configuration

Entitlement Filter Query for Request Start/End Date


Regards,
Rushikesh Vartak
If you find the response useful, kindly consider selecting Accept As Solution and clicking on the kudos button.

Hi Rushikesh,

Yes, we have used In end point page we have set Entitlement Filter Query for Request Start/End Date : and ev.customproperty36 = 'EndDate_Required'

In Entitlement_Type tab we have put

Ask For Start Date End Date While Request : Enabled

Config JSON for Request Dates : {"ENDDATEREQUIRED":"1"} 

This feature got enabled for entitlements not for specific entitlements 

try on privileged column once


Regards,
Rushikesh Vartak
If you find the response useful, kindly consider selecting Accept As Solution and clicking on the kudos button.

We do not have privileges set for this end point

set for some entitlement for testing


Regards,
Rushikesh Vartak
If you find the response useful, kindly consider selecting Accept As Solution and clicking on the kudos button.

Config JSON for Request Dates : {"ENDDATEREQUIRED":"0"} 


Regards,
Rushikesh Vartak
If you find the response useful, kindly consider selecting Accept As Solution and clicking on the kudos button.

hnalluri94
New Contributor II
New Contributor II

Its the same after we changed it 0. All entitlements are  being shown