Can we put delay between two consecutive jobs in the same trigger chain?

Version - 5.5 SP3.11

 

Thanks,

Sumaiya Babu

5 REPLIES 5

pmahalle
Valued Contributor II
Valued Contributor II

Hi @SUMAIYA_BABU ,

Not it’s not possible to put delay in two job in the same trigger chain.

If you want delay, schedule it separately as per requirement.


Regards,

Pandharinath Mahalle(Paddy)
If this reply answered your question, please Accept it As Solution to help others who may have a similar problem.

dgandhi
All-Star
All-Star

No this doesnt seem to be feasible.

 

Thanks,
Devang Gandhi
If this reply answered your question, please click the Accept As Solution button to help future users who may have a similar problem.

SUMAIYA_BABU
New Contributor III
New Contributor III

I have two provisioning jobs in same trigger chain , one after the other - each picking up two different types of tasks. But seems like the trigger chain stops at the first wsretry and the second one is never run.

Is it possible to have one wsretry job to run only on successful completion of another wsretry job?

pmahalle
Valued Contributor II
Valued Contributor II

Hi @SUMAIYA_BABU ,

Enabled the Enable blocking WSRETRY option in Global Configurations --> Preferences to add multiple WSRETRY jobs in the same trigger chain.

pmahalle_0-1689358581303.png

Refer below forum for details:

https://forums.saviynt.com/t5/did-you-know/did-you-know-you-can-now-trigger-chain-provisioning-job/m...


Regards,

Pandharinath Mahalle(Paddy)
If this reply answered your question, please Accept it As Solution to help others who may have a similar problem.

Have you checked below document?

https://forums.saviynt.com/t5/did-you-know/did-you-know-you-can-now-trigger-chain-provisioning-job/m...

 

 

Thanks,
Devang Gandhi
If this reply answered your question, please click the Accept As Solution button to help future users who may have a similar problem.