Can we put delay between two consecutive jobs in the same trigger chain?
Version - 5.5 SP3.11
Thanks,
Sumaiya Babu
Solved! Go to Solution.
07/14/2023 10:40 AM
Hi @SUMAIYA_BABU ,
Not it’s not possible to put delay in two job in the same trigger chain.
If you want delay, schedule it separately as per requirement.
07/14/2023 10:57 AM
No this doesnt seem to be feasible.
07/14/2023 11:11 AM
I have two provisioning jobs in same trigger chain , one after the other - each picking up two different types of tasks. But seems like the trigger chain stops at the first wsretry and the second one is never run.
Is it possible to have one wsretry job to run only on successful completion of another wsretry job?
07/14/2023 11:19 AM - edited 07/14/2023 11:23 AM
Hi @SUMAIYA_BABU ,
Enabled the Enable blocking WSRETRY option in Global Configurations --> Preferences to add multiple WSRETRY jobs in the same trigger chain.