Hi,


We are on 5.5SP2 and working with future dated tasks and due to this our list of pending tasks is growing and we would like to use analytics to show pending tasks that are NOT to be executed on future dates.


Does anyone know which table/fields hold the information on when the future dated tasks needs to be executed?

This message was previously posted on Saviynt's legacy forum by a community user and has been moved over to this forum for continued exposure.
3 REPLIES 3

Community_User
Saviynt Employee
Saviynt Employee
Originally posted on November 24 2020 at 03:15 UTC

arstasks is the table containing infirmation on tasks.


Thanks

Ajay

This message was previously posted on Saviynt's legacy forum by a community user and has been moved over to this forum for continued exposure.

Community_User
Saviynt Employee
Saviynt Employee
Originally posted on November 24 2020 at 08:43 UTC

Thanks, we are aware of this table, however we are not able to identify the field that holds the date on which the pending task needs to be processed.

This message was previously posted on Saviynt's legacy forum by a community user and has been moved over to this forum for continued exposure.

Community_User
Saviynt Employee
Saviynt Employee
Originally posted on November 27 2020 at 05:03 UTC

Pls check the startdate for the tasks for future date it would be a future date.