and more in a single search tool across platforms. Read the announcement here. |
04/12/2022 01:05 PM
Hi,
We are on 5.5SP2 and working with future dated tasks and due to this our list of pending tasks is growing and we would like to use analytics to show pending tasks that are NOT to be executed on future dates.
Does anyone know which table/fields hold the information on when the future dated tasks needs to be executed?
Solved! Go to Solution.
04/12/2022 02:20 PM
arstasks is the table containing infirmation on tasks.
Thanks
Ajay
04/12/2022 02:20 PM
Thanks, we are aware of this table, however we are not able to identify the field that holds the date on which the pending task needs to be processed.
04/12/2022 02:20 PM
Pls check the startdate for the tasks for future date it would be a future date.
Thanks
Ajay